40 MVA
Transformer T1
34 L/s
Underground well
4.4 km
Internal roads
120
Solar streetlights
Guard at the access gatehouse Electrical substation Switching vaults Well and water tank Wastewater treatment plant Trucks at the industrial park entrance El Molle dining hall AdminObraje team at the industrial park
AdminObraje logo, management of El Obraje Industrial Park
01 / 09 · Security
24/7
private security and access control
Guard at the access gatehouse
01 · Security and access

You always know who's coming in

24/7 private security.
Access with biometric technology and license-plate reading.
QR-code ID badge for employees.
Prior authorization from the company for visitors and suppliers.
24/7 monitoring center with video analytics and body cameras on security staff.
“The facilities meet occupational safety and physical security standards, something very important these days.”
UMCO logo, company at El Obraje Industrial ParkJesús Rojas · Production Manager, UMCO Ecuador S.A.
Electrical substation
02 · Power

Its own substation, with spare capacity today

The industrial park has its own 40 MVA electrical substation. The companies already installed use 10 MVA, leaving 30 MVA available for new plants.

10
30 MVA free
+40 MVA
In useAvailable todayPlanned upgrade
Today: a 40 MVA transformer in operation, fed by two 138 kV lines from the Santa Rosa substation.
Upgrade: a second 40 MVA transformer brings total capacity to 80 MVA.
Switching vaults
03 · Power grid

Your electrical connection is already built

The medium-voltage network is underground and reaches switching vaults distributed around the industrial park. Your plant simply connects to the vault closest to your lot.

Dead-front safetySealed pad-mounted equipment: no energized part is exposed to people moving around the industrial park.
Business continuityIf a building has an electrical fault, only that section is isolated. The other factories keep operating.
Maintenance by sectionSpecific sections of the network can be serviced, depending on technical conditions.
Flexibility and upgradesIf your plant's demand grows, loads are redistributed from the vault quickly and safely.
Fast fault isolationIn a short circuit, the protections act immediately and shield the main substation from a widespread blackout.
The industrial park's well and water tank
04 · Drinking water

Its own water, treated on site

An underground well of up to 34 L/s supplies the industrial park, and the modular 3 to 10 L/s drinking-water plant (PTAP) treats the water before it reaches your lot. The 34 L/s is the well's flow rate, not a guaranteed flow per company: availability depends on your requirement.

Well
34 L/s
→
Plant
PTAP 3–10 L/s
→
Reaches
Your lot
Fire-protection networkUnderground network with hydrants throughout the industrial park and a stand-alone pumping system. Storage in a 250 m³ tank.
Wastewater treatment plant
05 · Wastewater

Communal wastewater treatment plant (PTAS)

The industrial park has two separate sewer networks. The sanitary network carries wastewater to the communal PTAS; the storm network collects rainwater and treated water.

Sanitary network
Wastewater → PTAS
Storm network
Rainwater and treated water
Moving bed biofilm reactor (MBBR) biological treatment, with chlorination and sludge handling.
Continuous monitoring of BOD, COD and suspended solids, under current environmental regulations.

By municipal ordinance, each company treats its wastewater before discharging it into the sanitary sewer.

Trucks at the industrial park entrance
06 · Roads

Designed for heavy cargo

4.4 km
length
16 m
width · 12 m roadway
6 axles
up to 45 t
400
kg/cm² · paving stone
1.80 m
bike lane · 2 m sidewalks
120
solar LED streetlights

Vertical and horizontal signage throughout the industrial park, for vehicles and pedestrians.

Acceleration and deceleration lanesSafe entry and exit from the E35Deceleration lane on the E35 toward the industrial park entrance
El Molle dining hall
07 · Dining and catering

“El Molle” dining and catering

The industrial park's service center serves your company in three ways. The services are also open to companies from outside the site.

1.A dining hall for your staff, with capacity for 200 people.
2.Catering delivered directly to your plant.
3.Event space rental.
Punto Verde recognition · Eco Structure Punto Verde certification
Sustainable construction
AdminObraje team at the industrial parkAdminObraje logo, management of El Obraje Industrial Park
08 · AdminObraje

One team runs the entire industrial park

AdminObraje handles infrastructure maintenance, environmental services and machinery rental. You request everything in one place.

09 · Telecommunications

Fiber to every lot

Single-mode fiber optics: a 48-strand backbone and 4 strands to each lot's box. Fiber deployment with Puntonet began in 2022.

4 dedicated strands
per lot
Why did UMCO choose El Obraje?
“The first reason was the infrastructure: […] the most modern transformer station in the country.”
UMCO logo, company at El Obraje Industrial Park Jesús Rojas · Production Manager, UMCO Ecuador S.A.

Visit the industrial park and see it for yourself.

WhatsAppBook a visit →